Work started at Ostend Airport, closure of…

The demolition and earthworks started today. These works will take about two weeks. The foundation, sub-layers and top layer are then laid. The sewerage works are also being carried out at the same time. The new LED lighting will be installed from the end of February. To limit inconvenience, the contractor always works between 6 a.m. and 10 p.m. Night work will only occur in unforeseen circumstances.

The airport management emphasizes that the works on the runway will not lead to an increase in capacity. Due to the renovation, larger aircraft will not be able to land at the airport.