A precision job for road workers on the A27 at the Hooipolder junction: a tunnel bin of 6300 tons was pushed under the highway on Thursday night. This underpass must ensure a better flow. Of the job

The underpass had to travel a distance of 112.5 meters. The colossus was therefore attached to 96 lifting equipment and lifted five centimeters up on rails at night.

Three push pussies moved the construction into the A27 at ten meters per hour. After retiring, the soil was supplemented again. 20,000 cubic meters have been excavated to be able to build up the slider.

View the timelapse here:

Also, asphalt layers and lines must be applied again, lampposts, light towers, cables and guardrails are placed back and a detection systems for traffic jams are installed. On Monday morning at five o’clock the road must be open again for traffic.