The railway deck is the roof of the rail underpass. Now that it is in place, a few meters of land are being excavated under the Spoordek for the construction of a road and a cycle path. Next to the Spoordek, a bridge is being built over the Zuidtangent, where a new road has to be.

Again trains on Monday

Now that the Spoordek is in place, the track must be restored on the route. The contractor expects this to take another 66 hours, writes Regional city central. According to ProRail and the contractor, trains have to run again on the new concrete trainek. Travelers between Alkmaar and Heerhugowaard have then no longer to take the bus.

Next Monday, the work of ProRail on the track between Heerhugowaard and Den Helder will in all probability will also be completed. ProRail has replaced railway bridges there at a number of locations and Den Helder Zuid station has been given a new look.